Council has received the final report of the geotechnical investigation to guide solutions for the reconstruction of Naughtons Gap Road.
Transport for NSW is reviewing the Geotechnical Assessment and Recommended Remediation report and providing comment back to Council. Once this is complete, final approval for the funding will occur and Council will tender the works.
The project program has Council issuing the tender in June 2023 with a tender report tabled at the August 2023 Council meeting. Construction can commence immediately following the appointment of the successful contractor.
Reconstruction is expected to take up to tweve months to complete with the aim of having the road open to the public before Christmas 2024 subject to weather conditions.
Watch the video for a detailed explanation of the reconstruction process.